WHEX Clay Screening & Processing

This project, located at 10,000 ft elevation, involved the excavation, hauling, and screen processing of 1/2 million cubic yards of topsoil and  clay overburden into appropriate stockpiles. Topsoil was stripped and hauled as excavation progressed, and the clay material was processed to meet specific gradation requirements. JHL was responsible for maintaining safe working conditions around the stockpile areas and removing any reject material to a designated location.

Project Summary

  • 13,400 CY of topsoil removal on 2:1 slope
  • 321,500 CY of Clay removed along 4 different highwall benches
  • 61,940 excavator buckets fed into the plant
  • Soil liner fill processing
  • 200,000 CY of screened material produced
  • 948 hours of run time of screening operation with reject backhaul and stockpiling of accepted materials.
  • Maintain operations
  • Stormwater controls

Location

Confidential

Owner

Confidential

engineer

Confidential
Procore

Related Projects

View All Projects
photo of FSW Headquarters

Centennial, CO

FSW Headquarters

photo of Global Village Academy Northglenn

Northglenn, CO

Global Village Academy Northglenn

photo of Mrachek Middle School

Aurora, CO

Mrachek Middle School